Digest: Tây Ninh advances renewables, DPPA and storage under Resolution 70
Tây Ninh has 19 grid-connected renewable energy plants totaling 1,201.4 MW and seeks to bring forward about 1,250 MW of solar capacity and finalize DPPA and BESS mechanisms.

Tây Ninh has 19 grid-connected renewable energy plants totaling 1,201.4 MW and seeks to bring forward about 1,250 MW of solar capacity and finalize DPPA and BESS mechanisms.
VietnamPlus reported on October 17, 2026 that Tây Ninh is developing clean power, storage and direct power purchase agreements (DPPA) under Resolution 70-NQ/TW on energy security. The province has 19 renewable energy plants connected to the 220 kV and 110 kV grids, with combined capacity of 1,201.4 MW.
The province’s centralized solar project list for 2025–2030 comprises seven projects totaling 718 MW. Construction has begun on the 450 MW Dầu Tiếng 5 project, with investment of VND 7,774 billion; commercial operation is expected in December 2027, supplying more than 808 million kWh annually.
According to Xuân Cầu Holdings chairman Tô Dũng, Dầu Tiếng 5 is among the first projects to apply DPPA, supplying green electricity to large power users. Tây Ninh also plans to develop wind, biomass, waste-to-energy and LNG cogeneration, while studying floating solar alongside water resource protection.
The province has requested that approximately 1,250 MW of solar capacity be brought forward from 2031–2035 to 2026–2030 and that DPPA and battery energy storage system (BESS) mechanisms be finalized soon. Investment procedures, land issues, site clearance and transmission constraints need coordinated resolution to implement projects and enable renewable power delivery to the grid.
Source: Nghị quyết 70 mở đường cho Tây Ninh bứt phá thành trung tâm năng lượng tái tạo