According to Tuổi Trẻ on November 25, 2026, Vietnam’s Ministry of Industry and Trade warned that slow investment in generation and grids threatens electricity supply in 2027–2030. Many major power projects may miss their planned commissioning dates before 2030 under Power Development Plan VIII.
Around 127 GW of generating capacity needs to enter operation by 2030, but commissioned capacity accounts for only 5%. About 9% is under construction, 28% has investors selected but construction has not started, and 12% has investment policy approval but no selected investors. Around 45% has yet to receive investment policy approval.
Of 18 LNG power projects totaling more than 20,000 MW, only LNG Hiệp Phước is considered capable of meeting its schedule. Of 16 hydropower projects with selected developers, only two are under construction. Projects face obstacles involving investment procedures, land, transmission routes and site clearance.
EVN proposed easing credit and long-term financing constraints and supporting site clearance to accelerate projects. A ministry-led conference assessed that system operation would face multiple challenges in 2027 and greater difficulties in 2028. Electricity demand is expected to rise about 10% from the 2026 base; El Nino could persist until around June 2027, while global economic conditions could affect supply chains and imported coal and LNG prices.
Source: Cấp bách ngăn thiếu điện - Kỳ 1: Chỉ 5% dự án vận hành, lo nhiều nguồn điện lớn 'lỡ hẹn'